Use this earned schedule table to answer the following questions:
| Month-1 | Month-2 | Month-3 | Month-4 | Month-5 | Month-6 | Month-7 | |
| PV USD | USD-125 | USD 275 | USD 500 | USD 875 | USD 1485 | USD 2325 | USD 2670 |
| EV USD | USD-50 | USD 120 | USD 255 | USD 420 | USD 715 | USD 865 | USD 0 |
I) determine the schedule performance index (t) for this project at the end of Month 6
II) interpret the result