Question: QUESTION 4 Use this earned schedule table to determine the schedule performance index (t) for this project at the end of Month 6. PVS) Month

QUESTION 4 Use this earned schedule table to
QUESTION 4 Use this earned schedule table to determine the schedule performance index (t) for this project at the end of Month 6. PVS) Month 1 $125 $50 Month 2 $275 $120 Month 3 $500 $255 Month 4 $875 $420 Month 5 $1,485 $715 Month 6 $2,325 $865 Month 7 $2,670 $0 EV ($) 0.21 e 0.38 0.71 0.54