Question: Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 22 months. and
Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 22 months. and the project variance is 16.
a) The probability that the project will be completed in 6 months
b) The probability that the project will be completed in 21 months
c) The probability that the project will be completed in 26 months
d) The probability that the project will be completed in 38 months e) The due date that yields a 95% chance of completion