Question: Using the chart below along with the provided heuristics, and predetermined cycle time, assign tasks to workstations. Your answer should clearly indicate which task(s) are

  1. Using the chart below along with the provided heuristics, and predetermined cycle time, assign tasks to workstations. Your answer should clearly indicate which task(s) are completed at which workstations, and in what order. (Hint: drawing a precedence diagram will help to visualize required sequence of tasks)

Task

Immediate Predecessor

Time (in minutes)

A

----

4

B

----

3

C

----

2

D

A

2

E

B,C

4

F

D,E

2

G

F

3

H

F

2

I

G,H

1

J

I

2

Primary Heuristic: Assign tasks in order of shortest processing time

Tiebreaker Heuristic: Assign tasks in order of greatest number of following tasks

Use Cycle Time: 6 minutes

2. In order to calculate normal time for a stopwatch time study, a performance rating factor is used. If we observe an individual who works at a pace 12% faster than average, what performance

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!