Question: Using the chart below along with the provided heuristics, and predetermined cycle time, assign tasks to workstations. Your answer should clearly indicate which task(s) are
- Using the chart below along with the provided heuristics, and predetermined cycle time, assign tasks to workstations. Your answer should clearly indicate which task(s) are completed at which workstations, and in what order. (Hint: drawing a precedence diagram will help to visualize required sequence of tasks)
| Task | Immediate Predecessor | Time (in minutes) |
| A | ---- | 4 |
| B | ---- | 3 |
| C | ---- | 2 |
| D | A | 2 |
| E | B,C | 4 |
| F | D,E | 2 |
| G | F | 3 |
| H | F | 2 |
| I | G,H | 1 |
| J | I | 2 |
Primary Heuristic: Assign tasks in order of shortest processing time
Tiebreaker Heuristic: Assign tasks in order of greatest number of following tasks
Use Cycle Time: 6 minutes
2. In order to calculate normal time for a stopwatch time study, a performance rating factor is used. If we observe an individual who works at a pace 12% faster than average, what performance
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts