Question: Using the chart of activity data provided, what is expected standard deviation for activity B is 10 weeks 3.33 weeks 2.78 weeks 1.67 weeks
Using the chart of activity data provided, what is expected standard deviation for activity B is 10 weeks 3.33 weeks 2.78 weeks 1.67 weeks