Question: Using the information created on Tab 2. create the corresponding Gantt Chart a. Clearly identify the critical path b. Note all non-critical items and the
| Using the information created on Tab 2. create the corresponding Gantt Chart | |||||||
| a. Clearly identify the critical path | |||||||
| b. Note all non-critical items and the slack or float associated them | |||||||
| c. Start date for the project is January 1, 2022 |
| Door Mirror Assembly | ||
| Task Name | Duration | Predecessors |
| Door Mirror Assembly | 0 days | |
| Design Door Mirror Ass'y | 5 days | A |
| Door Casing Mold | 0 days | B |
| Design Casing Mold | 2 days | C |
| Build Casing Mold | 5 days | D |
| Purchase Raw Material | 2 days | D |
| Run Sample Casings | 1 day | E,F |
| QC Check Sample Casing | 1 day | G |
| Run Production Casing | 3 days | H |
| REFLECTIVE MIRROR | 0 days | B |
| Mirror - Existing - In Stock | 0 days | J |
| CAMERA INTERFACE | 0 days | B |
| Design Interface | 3 days | L |
| Build Interface | 2 days | M |
| Install Interface | 1 day | N |
| CAMERA | 0 days | B |
| Design Camera | 5 days | P |
| Electrical Cables - Existing | 0 days | Q |
| Build Camera | 3 days | Q,R |
| Test Camera | 2 days | S |
| Final Assembly | 0 days | I,K,O, T |
| Door Mirror Assembly | 3 days | U |
| Inspect Mirror Assembly | 1 day | V |
| Ship Mirror Assembly | 1 day | W |

Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock