Question: Using the information from exercise 8.8, in the BOOK Contemporary Project Management input the data into MS project. Display and print the schedule in a

Using the information from exercise 8.8, in the BOOK Contemporary Project Management input the data into MS project. Display and print the schedule in a Gantt chart format as shown in exhibit 8.19 IMMEDIATE PREDECESSOR ACTIVITY DAYS 2 3 B, C D, E, F EXHIBIT 8.19 GANTT CHART EXAMPLE Time in workdays 15 20 25 30 35 40 45 50 55 60 65 70 0 5 10 Activity Determine new product features Acquire prototype materials Produce prototype Design marketing campaign Design graphics Conduct marketing Perform sales calls