Question: Using the information from the following table, create an AON network activity diagram: a. Calculate each activity TE (rounding to the nearest integer), Preceding Activities

Using the information from the following table, create an AON network activity diagram:

a. Calculate each activity TE (rounding to the nearest integer),

Using the information from the following table, create an AON network activity

Preceding Activities Activity Best Likely Worst A 12 15 25 B A 4 6 11 12 12 30 D 8 15 20 B, C A E 7 12 15 F E 9 9 U OWO I - - 42 19 G 13 17 D, E F H 5 10 15 G 11 13 20 2 3 6 G H J,1 K 8 12 22