Question: Using the PERT method review the following data for a project that should be scheduled using CPM: b. What is the critical path? A-D-G-H A-D-F-H

Using the PERT method review the following data for a project that should be scheduled using CPM: b. What is the critical path? A-D-G-H A-D-F-H A-C-F-H B-E-G.H c. What is the expected project completion time? (Round your answer to 3 decimal places.) Project completion time days b. What is the critical path? A-D.G.H A-D.F.H A.C.F.H B-E-G.H c. What is the expected project completion time? (Round your answer to 3 decimal places.) Project completion time days d. What is the probability of completing this project within 20 days? (Do not round intermediate calculations. Round your answer to 4 decimal places.) Probability