Question: Using the PERT method review the following data for a project that should be scheduled using CPM: b. What is the critical path? B.E.G-HO A.D.G.H

Using the PERT method review the following data for a project that should be scheduled using CPM: b. What is the critical path? B.E.G-HO A.D.G.H A.C.F.H A.D.F.H c. What is the expected project completion time? (Round your answer to 3 decimal places.) b. What is the critical path? B-E-G-H A-D.G-H A.C-F-H A-D.F-H c. What is the expected project completion time? (Round your answer to 3 decimal places.) Project completion time days d. What is the probability of completing this project within 19 days? (Do not round intermediate calculations. Round your answer decimal places.) Probability