Question: Using the PERT method review the following data for a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES ( DAYS ) ACTIVITY a

Using the PERT method review the following data for a project that should be scheduled using CPM:
IMMEDIATE PREDECESSORS TIMES (DAYS)
ACTIVITY a m b
A 147
B 2613
C A 114
D A 234
E B 246
F C,D 159
G D,E 129
H F,G 369
b. What is the critical path?
multiple choice
A-C-F-H
B-E-G-H
A-D-G-H
A-D-F-H