Question: Using the PERT technique, let's say you estimate an activity to most likely take 2 0 hours. The best case is 1 0 hours, and

Using the PERT technique, let's say you estimate an activity to most likely take 20 hours. The best case is 10 hours, and the worst case is 30 hours. What is the expected time?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!