Question: Using the PERT technique, let's say you estimate an activity to most likely take 2 0 hours . The best case is 1 0 hours

Using the PERT technique, let's say you estimate an activity to most likely take
2
0
hours. The best case is
1
0
hours, and the worst case is
3
0
hours. what is the standard deviation