Question: Using the PERT technique, let's say you estimate an activity to most likely take 2 0 hours. The best case is 1 0 hours (

Using the PERT technique, let's say you estimate an activity to most likely take 20 hours. The best case is 10 hours (assuming everything goes right), and the worst case (assuming something goes wrong) is 30 hours. What is the expected time?
 Using the PERT technique, let's say you estimate an activity to