Question: Using the project management data in the table below, answer the proceeding questions. Activity Preceding Activity Optimistic Duration ( Days ) Most Likely Duration (

Using the project management data in the table below, answer the proceeding questions.
Activity
Preceding Activity
Optimistic Duration (Days)
Most Likely Duration (Days)
Pessimistic Duration (Days)
CrashCost ($)(Per Day)
MaxCrash(Days)
A
-
30
32
33
-
0
B
A
32
36
39
1,125
1
C
A
32
36
39
1,136
2
D
B, C
30
31
33
2,147
1
E
D
24
27
29
1,109
2
F
D
42
49
53
2,158
1
G
D
32
35
39
1,178
0
H
E, F, G
26
29
35
2,320
1
What is the expected duration of the project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!