Question: Using the project management data in the table below, answer the proceeding questions. Activity Preceding Activity Optimistic Duration ( Days ) Most Likely Duration (
Using the project management data in the table below, answer the proceeding questions.
Activity
Preceding Activity
Optimistic Duration Days
Most Likely Duration Days
Pessimistic Duration Days
CrashCost $Per Day
MaxCrashDays
A
B
A
C
A
D
B C
E
D
F
D
G
D
H
E F G
What is the expected duration of the project?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
