Question: Using the project management data in the table below, answer the proceeding questions. Activity Preceding Activity Optimistic Duration ( Days ) Most Likely Duration (
Using the project management data in the table below, answer the proceeding questions.
Activity Preceding Activity Optimistic Duration Days Most Likely Duration Days Pessimistic Duration Days Crash
Cost $
Per Day Max
Crash
Days
A
B A
C A
D B C
E C
F C
G D
H E F G
What is the expected duration of the project?
It is imperative that the project be crashed by days. Which activities, in order of crash selection, shall be crashed?
What is the estimated total crashing cost incurred?