Question: Using the project management data in the table below, answer the proceeding questions. Activity Preceding Activity Optimistic Duration ( Days ) Most Likely Duration (

Using the project management data in the table below, answer the proceeding questions.
Activity Preceding Activity Optimistic Duration (Days) Most Likely Duration (Days) Pessimistic Duration (Days) Crash
Cost ($)
(Per Day) Max
Crash
(Days)
A -121316-0
B A 69101,2252
C A 1416201,2364
D B, C 1112131,2473
E C 69122,1092
F C 2630341,9586
G D 1315192,4780
H E, F, G 410171,4732
What is the expected duration of the project?
It is imperative that the project be crashed by 7 days. Which activities, in order of crash selection, shall be crashed?
What is the estimated total crashing cost incurred?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!