Question: Using the table below, draw a network diagram in the PDM style and perform CPM Analysis to: table [ [ Activty , table
Using the table below, draw a network diagram in the PDM style and perform CPM Analysis to:
tableActivtytableDurationDaysPredecessorsABACADBEBFCGD E FHFIG H
a Identify all project paths and the estimated duration of each
b Identify the estimated shortest project duration
c Identify the Critical Path and its duration
d Calculate Activity Slack using the Forward and Backward pass technique
e Answer the following questions:
If activity is delayed days, can be delayed without affecting the project finish date?
If the duration of activity takes extra days, how long will the project take to finish?
If activity takes days to complete, what is the earliest day that activity will finish?
Copy and paste the object to the left once for each activity replacing the with the duration and the Activity with the "name" from the table above.
Arrange to reflect the dependencies noted above. Insert arrows to complete the Network Diagram. Then delete this box!
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock