Question: Using the table below, draw a network diagram in the PDM style and perform CPM Analysis to: table [ [ Activty , table

Using the table below, draw a network diagram in the PDM style and perform CPM Analysis to:
\table[[Activty,\table[[Duration],[(Days)]],Predecessors],[A,3,-],[B,4,A],[C,2,A],[D,1,B],[E,5,B],[F,8,C],[G,6,D, E, F],[H,7,F],[I,2,G, H]]
a. Identify all project paths and the estimated duration of each
b. Identify the estimated shortest project duration
c. Identify the Critical Path (and its duration
d. Calculate Activity Slack using the Forward and Backward pass technique
e. Answer the following questions:
If activity E is delayed 2 days, can G be delayed without affecting the project finish date?
If the duration of activity D takes 3 extra days, how long will the project take to finish?
If activity F takes 11 days to complete, what is the earliest day that activity G will finish?
Copy and paste the object to the left (once for each activity) replacing the d with the duration and the Activity with the "name" from the table above.
Arrange to reflect the dependencies noted above. Insert arrows to complete the Network Diagram. Then delete this box!
 Using the table below, draw a network diagram in the PDM

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!