Question: What is a typical consequence of overly optimistic task time estimates in the project planning phase? 1 point You create accurate estimates that increase team

What is a typical consequence of overly optimistic task time estimates in the project planning phase? 1 point You create accurate estimates that increase team morale. The team can clearly communicate potential risks for the project. You overlook potential risks that delay your plans. Stakeholders and project sponsors leave the project