Question: What is the earliest completion time for this project? O A. 19 weeks OB. 21 weeks O C. 18 weeks OD. 20 weeks Activity Predecessor

What is the earliest completion time for this

What is the earliest completion time for this project? O A. 19 weeks OB. 21 weeks O C. 18 weeks OD. 20 weeks Activity Predecessor Time(weeks) A - - 8 BAT6 C -- T4 E L A 11 FB T3 GD,E,F 11