Question: asap please Table A Activity Predecessor Time(weeks) A .. 8 B A 6 C - 4 D C 9 E A 11 F B 3
asap please
Table A Activity Predecessor Time(weeks) A .. 8 B A 6 C - 4 D C 9 E A 11 F B 3 G D, E, F 1 Using Table A, what is the earliest completion time for this project? Multiple Choice 18 weeks 19 weeks 20 weeks D C 9 E A 11 F B 3 G D, E, F 1 sing Table A, what is the earliest completion time for this project? Multiple Choice O 18 weeks. 19 weeks 20 weeks 21 weeks