Question: 2 5 What is the expected time for activity B? Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B, C A D

25
 
 
What is the expected time for activity B? Time Estimates (days) Activity

What is the expected time for activity B? Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B, C A D 38 50 62 B E 90 97 108 CD End 85 100 115 FL 19 25 31 E End 91 98 115 F End 62 42 99.7 days 100 days 98.0 days 98.3 days 97.7 days 65 55 68