Question: Pessimistic Consider the following work breakdown structure: Duration Estimates (Days) Activity Precedes Optimistic Most Likely Start U,V U W 35 50 V W.X 28 40

Pessimistic Consider the following work breakdown
Pessimistic Consider the following work breakdown structure: Duration Estimates (Days) Activity Precedes Optimistic Most Likely Start U,V U W 35 50 V W.X 28 40 W Z 26 35 X Y 28 40 Y Z 26 29 z End 36 60 What is the estimated expected (mean) time for project completion? 180 days 255 days 145 days 170 days 135 days 65 52 44 52 38 84

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!