Question: What is the slack time? A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate

What is the slack time? A project for improving a

What is the slack time?

A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A 2 B 8 5 A B, C D 12 E 9 B F 4 D G 6 E F, G 7 a. Choose the correct network diagram below. MA OB S 6)