Question: What would be the critical path ( s ) if task B started 1 day earlier than planned and finished 1 5 days later than

What would be the critical path(s) if task B started 1 day earlier than planned and finished 15 days later than planned.
A. ADFGH
B. AD F G H and A B G H
C. ABGH
D. All of the paths would then be critical
QUESTION 5
The Critical path in this example is A>B>G>H
True
False
 What would be the critical path(s) if task B started 1