Question: When there is a 3 - day lag between the end of activity A and the start of activity B , then? Activity B has

When there is a 3-day lag between the end of activity A and the start of activity B, then?
Activity B has to wait exactly 3 days after the completion of activity A before it can start
Activity B has to wait at least 3 days after the completion of activity A before it can start
Activity B has to wait at most 3 days after the completion of activity A before it can start
Activity B cannot take more than 3 days in duration
 When there is a 3-day lag between the end of activity