Question: . Which activities have slack, and how much? multiple choice 2 D , 1 week; E , 2 weeks. C , 1 week; E ,
Which activities have slack, and how much?
multiple choice
D week; E weeks.
C week; E weeks.
B weeks; E weeks.
C weeks; F weeks.
Here is a table of normal and crash times and costs.
ACTIVITY NORMAL TIME CRASH TIME NORMAL COST CRASH COST
A $ $
B
C
D
E
F
G
d Which activities would you shorten to cut two weeks from the schedule in a rational fashion?
multiple choice
A C
B C
B D
A E
d What would be the total incremental cost?