Question: . Which activities have slack, and how much? multiple choice 2 D , 1 week; E , 2 weeks. C , 1 week; E ,

. Which activities have slack, and how much?
multiple choice 2
D,1 week; E,2 weeks.
C,1 week; E,2 weeks.
B,2 weeks; E,2 weeks.
C,2 weeks; F,3 weeks.
Here is a table of normal and crash times and costs.
ACTIVITY NORMAL TIME CRASH TIME NORMAL COST CRASH COST
A 76 $7,000 $8,000
B 215,0007,000
C 439,00010,200
D 543,0004,500
E 212,0003,000
F 424,0007,000
G 545,0008,000
d-1. Which activities would you shorten to cut two weeks from the schedule in a rational fashion?
multiple choice 3
A, C
B, C
B, D
A, E
d-2. What would be the total incremental cost?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!