Question: Which statement is false about project scheduling? a. the critical path always has a total slack of zero b. the early finish for a task
Which statement is false about project scheduling? a. the critical path always has a total slack of zero b. the early finish for a task is equal to the early start plus the task duration c. project crashing is an effort to optimize the project cost and duration d. slack time is defined as late start minus early start e. standard deviation of the critical path is the sum of the standard deviation of the activities on the critical path
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
