Question: Which statement is not true about project scheduling? a. the critical path always has a total slack of zero b. slack time is defined as
Which statement is not true about project scheduling? a. the critical path always has a total slack of zero b. slack time is defined as early start minus late start c. the early finish for a task is equal to the early start plus the task duration d. variance of the critical path is the sum of the variance of the activities on the critical path. e. project crashing is an effort to optimize the project cost and duration