Question: The following table lists the tasks and preceding tasks for a project. Draw the activity-on-node diagram for this project. Task Preceding Task None A B

 The following table lists the tasks and preceding tasks for a

The following table lists the tasks and preceding tasks for a project. Draw the activity-on-node diagram for this project. Task Preceding Task None A B B C, D E Choose the correct activity-on-node diagram below. O A. O B. +