Question: The following table lists the tasks and preceding tasks for a project. Draw the activity-on-node diagram for this project. Task Preceding Task A none B
The following table lists the tasks and preceding tasks for a project. Draw the activity-on-node diagram for this project.
Task Preceding Task
A none B A C B D C E B
Draw the correct activity-on-node(AON) diagram