Question: You have three projects consisting of three sequential tasks each (design, followed by production, followed by training). You have one crew for each task. Schedule
You have three projects consisting of three sequential tasks each (design, followed by production, followed by training). You have one crew for each task. Schedule to minimize penalties. *Note - the penalty starts each week past the deadline.
| Project | Design | Production | Training | Deadline | Penalty |
| A | 4 weeks | 7 weeks | 3 weeks | week 20 | $50k/week |
| B | 3 weeks | 5 weeks | 1 week | week 10 | $30k/week |
| C | 1 week | 4 weeks | 1 week | week 10 | $20k/week |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
