Question: You have three projects consisting of three sequential tasks each (design, followed by production, followed by training). You have one crew for each task. Schedule

You have three projects consisting of three

You have three projects consisting of three sequential tasks each (design, followed by production, followed by training). You have one crew for each task. Schedule to minimize penalty. (Don't use critical chain) Project Design Production Training Deadline Penalty A 4 weeks 7 weeks 3 weeks Week 20 $50K/week B 3 weeks 5 weeks 1 week Week 10 $30K/week 1 week 4 weeks 1 week Week 10 $20K/week