Question: You have three projects consisting of three sequential tasks each (design, followed by production, followed by training). You have one crew for each task. Schedule

You have three projects consisting of three sequential tasks each (design, followed by production, followed by training). You have one crew for each task. Schedule to minimize penalty. (Dont use critical chain)

Project

Design

Production

Training

Deadline

Penalty

A

4 weeks

7 weeks

3 weeks

Week 20

$50K/week

B

3 weeks

5 weeks

1 week

Week 10

$30K/week

C

1 week

4 weeks

1 week

Week 10

$20K/week

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock