Question: There are three projects consisting of three sequential tasks each (design, followed by production, followed by training). There is one crew for each task. Schedule
There are three projects consisting of three sequential tasks each (design, followed by production, followed by training). There is one crew for each task. Schedule the tasks and activities to minimize penalty.
| Project | Design | Production | Training | Deadline | Penalty |
| A | 4 weeks | 7 weeks | 3 weeks | Week 20 | $50K/week |
| B | 3 weeks | 5 weeks | 1 week | Week 10 | $30K/week |
| C | 1 week | 4 weeks | 1 week | Week 10 | $20K/week |