Question: You know that your project is behind because the cumulative EV is much . . ? Question 1 options: A ) higher than cumulative PV

You know that your project is behind because the cumulative EV is much ..?
Question 1 options:
A)
higher than cumulative PV.
B)
lower than cumulative PV.
C)
higher than cumulative AC.
D)
lower than cumulative CPI.