Question: You monitored figures on cost and planned / earned value for each individual project week until the data date at the end of the sixth

You monitored figures on cost and planned/earned value for each individual project week until the data date at the end of the sixth week. What is the status of this project at this date?
\table[[\table[[Project],[Week]],\table[[Actual],[Costs]],\table[[Earned],[Value]],\table[[Planned],[Value]]],[1,$75,000,$61,000,$67,000