Question: You monitored figures on cost and planned/earned value for each individual project week until the data date at the end of the sixth week. What

You monitored figures on cost and planned/earned value for each individual project week until the data date at the end of the sixth week. What is the status of this project at this date? Project Week Actual Costs Earned Value Planned Value 1 $75,000 $61.000 $67.000 $95.000 $79.000 $89.000 N x 3 $80,000 $102,000 $110.000 4 $115.000 $124.000 $121.000 5 $135.000 $133.000 $139.000 $125,000 $120,000 $131.000 The project is ahead of schedule and over budget The project is ahead of schedule and under budget The project is behind schedule and over budget The project is behind schedule and under budget