Question: Question 2: Calculate Earned Value Indicators Based on the following data: The Budget At Completion (BAC) cost of the project is estimated to be: $52,250.
Question 2: Calculate Earned Value Indicators Based on the following data: The Budget At Completion (BAC) cost of the project is estimated to be: $52,250. Earned value data is available for the first three weeks of the project (see below). The project is due to end on week four (4). Project Data Week 1 Week 2 Week 3 Week 4 Cumulative Actual Costs $5,000 $16,000 $37,800 Cumulative Planned Value $11,750 $22,000 $43,000 $52,250 Cumulative Earned Value $7,000 $22,000
Based on the question 2 data, represent the projects earned value status in a visual format. Your image need only include your AC, EV, and PV over the four-week project (see example chart at right). This chart can be done in Excel (or equivalent), or it can be drawn by hand (and then digitally scanned or photographed, and included in your assignment).
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts