Question: You need to develop a labor time estimate for a customer order of 30 network installations. It is estimated that the first installation will require
You need to develop a labor time estimate for a customer order of 30 network installations. It is estimated that the first installation will require 50 labor hours, and a learning curve of 80 percent is expected.
- How many labor-hours are required for the fifteenth installation?
- How many labor-hours are required to complete all 30 installations?
- If the average labor cost is $26 per hour, what is the total labor cost for installing all the networks?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts