Question: You plan your work on a Monday to Friday schedule. There is a holiday on Monday the 1 6 th . If the earliest an

You plan your work on a Monday to Friday schedule. There is a holiday on Monday the 16th.
If the earliest an activity can finish is Thursday the 12th, what is the Early Start time of the next activity in the sequence?