Question: The project network and table below show the expected number of weeks to complete a series of activities and the corresponding variances: a. Determine the
-1.png)
-2.png)
a. Determine the critical path and the earliest expected completion time.
b. What is the probability of completing the project in 24 weeks or less?
Activity Expected Duration, Weeks Variance. Weeks 10 4 Start End
Step by Step Solution
3.46 Rating (166 Votes )
There are 3 Steps involved in it
a Activity ES LS TS A 0 1 1 B 5 8 3 C 5 6 1 D 0 0 0 E 10 ... View full answer