Question: The following table provides the information necessary to construct a project network and project crash data: a. Construct the project network. b. Determine the maximum
The following table provides the information necessary to construct a project network and project crash data:
.png)
a. Construct the project network.
b. Determine the maximum possible crash time for the network, and crash the network the maximum amount possible.
c. Compute the normal project cost and the cost of the crashedproject.
Activity Activity CostIS) Activity Time(weeks) Activity Predecessor Hormal Crash ormal Crash 8 1,000 1,480 24 20 200 1400 700 1.190 10 6 500 0 11 5 550 730 20 14 7