Question: The following table provides the information necessary to construct a project network and project crash data: Construct the project network, and crash the network the
The following table provides the information necessary to construct a project network and project crash data:
.png)
Construct the project network, and crash the network the maximum amountpossible.
Activity Time (weeks)Cest s) Activity Activity Activity Predecess or Normal Crash Normal Crash 8 2,000 4400 14 91000 1,800 8 6 500 700 600 1300 4 2 500 3000 800 1600 7 3,000 4500 15 0 50008000 16 10 d. e
Step by Step Solution
3.38 Rating (176 Votes )
There are 3 Steps involved in it
Normal critical Normal critical path Project completion Normal Minimum project completion Crash ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
184-B-M-L-O-M (458).docx
120 KBs Word File
