Question: The project network for building a garage is shown in Figure 13.11 and includes data on activity times and their deviations. a. Develop a Monte

The project network for building a garage is shown in Figure 13.11 and includes data on activity times and their deviations.

a. Develop a Monte Carlo simulation model that can be used to generate a distribution of project completion times ( longest path from node 1 to 8).

b. Simulate 5 project completion experiences using random numbers from Appendix B. What is the expected project duration time?

Step by Step Solution

3.40 Rating (156 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Random numbers are drawn for each activity to determine its durat... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

517-B-M-L-O-M (3957).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!