Question: Three time estimates for a task in a project are as follows: Optimistic completion time = 4 weeks Most likely completion time = 9 weeks
Optimistic completion time = 4 weeks
Most likely completion time = 9 weeks
Pessimistic completion time = 15 weeks
Calculate the expected task variance.
Step by Step Solution
3.40 Rating (172 Votes )
There are 3 Steps involved in it
By using formula 122 we can calcula... View full answer