Question: A project has four activities (A, B, C, and D) that must be completed sequentially in order to complete the project. The probability distribution for
.png)
a. Use a random number procedure to simulate the completion time for each activity. Sum the activity times to establish a completion time for the entire project.
b. Use the simulation procedure developed in part a to simulate 20 completions of this project. Show the distribution of completion times and estimate the probability that the project can be completed in 35 weeks or less?
ro 5005 23312521242064 0550500500 678357121 02468 0
Step by Step Solution
3.47 Rating (157 Votes )
There are 3 Steps involved in it
a Activity Activity Time weeks Probability Random numbers ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
1086-B-M-L-O-M(6028).docx
120 KBs Word File
