Question: Assume you have collected the following data for your project. Its budget is $75,000 and it is expected to last four months. After two months,

Assume you have collected the following data for your project. Its budget is $75,000 and it is expected to last four months. After two months, you have calculated the following information about the project:
PV = $45,000
EV = $38,500
AC = $37,000
Calculate the SPI and CPI. Based on these values, estimate the time and budget necessary to complete the project? How would you evaluate these findings? Are they good news or bad news?)

Step by Step Solution

3.38 Rating (157 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

SPI EVPV 3850045000 86 CPI EVAC 3850037000 104 Estimated Time to Completion 186 x 4 months ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

663-B-M-L-P-M (2213).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!