Question: Consider the following Activity-On-Node (AON) project (activity completion times are in days). Refer to the figure. What is the slack time, in days, associated with
.png)
Refer to the figure. What is the slack time, in days, associated with activity D?
A.......................0
B.......................1
C.......................2
D.......................3
E.......................4
B D F
Step by Step Solution
3.45 Rating (165 Votes )
There are 3 Steps involved in it
B 1 Earliest time of completion is 3 5 2 10 L... View full answer