Question: Here is a network with the activity times shown in days: a. Find the critical path. b. The following table shows the normal times and
Here is a network with the activity times shown in days:
-1.png)
a. Find the critical path.
b. The following table shows the normal times and the crash times, along with the associated costs for each activity.
-2.png)
If the project is to be shortened by four days, show which activities, in order of reduction, would be shortened and the resultingcost.
B(3 F4) D5) G5 2) c4) ACTIVITY NORMAL TIME CRASH TIME NORMAL COST CRASH COST $7,000 5,000 9,000 3,000 2,000 4,000 5,000 $ 8,000 7,000 10,200 4,500 3,000 7,000 8,000
Step by Step Solution
3.39 Rating (165 Votes )
There are 3 Steps involved in it
a ACDFG b Activity Normal Time NT Crash Time CT Normal Cost NC Crash Cost CC NTCT Costday to expedit... View full answer